Miscellaneous and General Charges
Applicable w.e.f. July 2000
| 5/GA/119/10 |
Dtd . 19/06/2000 |
1. (A) Charges for hire of metering system where it is the property of the Board.
1. FOR 230/440 VOLTAGE
I. Single Phase Meter
| (1) | Without miniature Circuit breakers | - | Rs. 12.00 per meter per month |
| (2) | With Miniature circuit breaker | - | Rs. 16.00 per meter per month |
II. Poly Phase Meter
| (1) | Without miniature circuit breakers | - | Rs. 25.00 per meter per month |
| (2) | With Miniature circuit breaker | - | Rs. 32.00 per meter per month |
| (3) | LT METER WITH CTS | - | Rs. 45.00 per meter per month |
| (4) | DEMAND OR SPECIAL TYPE METER | - |
Rs. 184.00 per meter or 2.3% per Month per rupee of cost of metering System (comprising of meter, meter Box,cables, & CT units ). Whichever Is higher. |
III. For 11 KV Voltage
| (1) | Electro magnetic meter | - | Rs.920/- per meter per month. |
| (2) | Electro static meter | - | Rs.1540/- per meter per month |
IV. For 33 KV Voltage
| (1) | Electro magnetic meter | - | Rs.1560/- per meter per month. |
| (2) | Electro static meter | - | Rs. 2040/- per meter per month |
V. For 132 KV Voltage
| (1) | Electro magnetic meter | - | Rs.15630/- per meter per month. |
| (2) | Electro static meter | - | Rs.16120/- per meter per month |
VI. For 220 KV Voltage
| (1) | Electro magnetic meter | - | Rs.32,250/- per meter per month. |
| (2) | Electro static meter | - | Rs. 32730/- per meter per month |
VII.
For
Special Metering - (Such
as summation Metering etc.)
|
2.3%
of the cost of per metering and allied |
2. FOR 230/440 VOLTAGE
| a. | Changing or removing a Meter Board | - | Actual cost + 15%. |
| b. | Changing of meter at the consumer’s request. | - | Rs. 52/- |
| c. |
(I) |
Fle-sealing of cut-outs of the Board in the consumer’s premises, if seal is found broken. | - | Rs. 13.00 |
| (II) | Re-sealing of meters, M.D. indicators and instruments of the Board in the consumer’s Premises, if seal is found Broken. | |||
| (A) For single phase connections | ||||
|
(a1) L&F connection |
- | Rs.65.00 | ||
|
(a2) Power connections. |
- | Rs. 112.00 | ||
| (B) For Three phase LT connections | ||||
|
(b1) Industrial connections for loads upto 10 BHP. |
- | Rs. 214.00 | ||
|
(b2) Industrial connections for loads above 10 BHP. |
- | Rs.437.00 | ||
|
(b3) Irrigation consumers for loads upto 5 BHP. |
- | Rs.65.00 | ||
|
(b4) Irrigation consumers for loads above 5 BHP. |
- | Rs. 108.00 | ||
| (C) For all HT connections | - | Rs.. 865.00 | ||
| d. | Testing of installations | |||
|
(d1) The first test of a new installation or of an extension to any existing installation, if the installation is found to be not defective and if the wiring contractor or his representative is present at the test. |
- | NIL | ||
|
(d2) For the first or subsequent test of a new installation or of an extension to an existing Installation is found to be defective Or if the wiring contractor or his Representative fails to be present. |
- | Rs.130.00 payable in advance for each subsequent visit for purpose of testing. | ||
| e. | Replacing of cut-out fuses. | - | Rs. 13.00 for one fuse or more than one fuse, if all replaced at the same time. | |
| f. | Replacing consumer’s Fuses ( L.T.) | - | Rs. 11.00 if undertaken along with (c) (I) above otherwise Rs. 13.00 | |
| g. | Replacement of Missing meter cards. | - | Rs. 7.00 per card including Clerical charges. | |
| h. | Replacement of broken | - | Rs. 24.00 per glass,. | |
| i. | Reconnections | |||
|
(1) Up to 10 KW |
||||
|
At cut-outs |
- | Rs. 52.00 | ||
|
At overhead mains |
- | Rs.130..00 | ||
|
At underground mains |
- | Rs. 391.00 | ||
|
(2) Over 10 KW and upto 75 KW |
- | Add 25% to above charges | ||
|
(3) Over 75 KW (Special charges according to the condition of load) |
- | Actual plus 25% subject to minimum chargeable under (I) & (ii) above. | ||
| j. | Re-rating of installation when done at the request of the consumer | - | Rs. 97.00 per apparatus. | |