5.1 GENERATION

C.S.E.B is having 1786 MW of Thermal Power and 137.85 MW of Hydel Power Plants

THERMAL POWER STATION

1.0 KORBA EAST THERMAL POWER STATION ( 4 X 50 MW + 2 X 120 MW )

Power Generation : Korba East

Power Generation : Korba East

Korba East TPS is located at the East Bank of River Hasdeo and near Balco  Aluminium Factory having Installed capacity of 440 MW. The various units of the Power Station were commissioned on  dates given below :

Power House - II
Unit 1 ( 50 MW ) - 22/10/1966
Unit 2 ( 50 MW ) - 16/07/1967
Unit 3 ( 50 MW ) - 28/08/1968
Unit 4 ( 50 MW ) - 31/10/1968

The above units were de-rated to 40 MW w.e.f. 01/01/1990 by Central Electricity Authority (CEA). Refurbishment work of all the units has been completed. After completion of the work, the capacity of the 40 MW units has enhanced to 50 MW. Dates of re-commissioning after refurbishment are as follows: 

Unit 1 ( 50 MW ) - 03/03/2004
Unit 2 ( 50 MW ) - 12/09/2002
Unit 3 ( 50 MW ) - 09/12/2002
Unit 4 ( 50 MW ) - 03/10/2003

 

Power House - III
Unit 5 ( 120 MW ) - 24/03/1976
Unit 6 ( 120 MW ) - 05/04/1981

The load on these units was restricted to 90-95 MW due to various problems in Boiler side and design deficiencies. Refurbishment of these units has been completed and the units are running normally at 110 to 115 MW load. The dates of re-commissioning after refurbishment are as follows.

Unit 5 ( 120 MW ) - 03/03/2005
Unit 6 ( 120 MW ) - 08/10/2003

No.20-01/07/1928  Dtd.

02.0 KORBA EAST EXTENSION  THERMAL POWER STATION (  2 X 250 MW )

 

 

Korba East  Extension TPS is located at the East Bank of River Hasdeo . The various units of the Power Station were commissioned on  dates given below

Power House - I
Unit 1 ( 250 MW ) - 30/03/2007
Unit 2 ( 250 MW ) - 11/12/2007

3.0 KORBA WEST THERMAL POWER STATION (  4 X 210 MW )

Power Generaton : Korba West

Power Generation : Korba West

Korba West TPS is located by the side of Hasdeo Barrage. The various units of the Power Station were commissioned on following dates as given below -

Power House - I
Unit 1 ( 210 MW ) - 21/08/1983
Unit 2 ( 210 MW ) - 31/03/1984
Power House - II
Unit 3 ( 210 MW ) - 28/03/1985
Unit 4 ( 210 MW ) - 13/03/1986
 HYDEL (0.85 MW) - 12/01/2003

CO- GENERATION  POWER  STATION

The units of co generation kawardha  Power Station ( 1 x 6 MW ) was commissioned on dated 10.08.2006

HYDEL POWER  STATION

1.0 HASDEO BANGO HYDEL POWER STATION ( 3 X 40 MW  )

The units of Hasdeo Bango Hydel Power Station were  commissioned during 1994-1995. The date of commissioning of units are given as below -

Unit 1 ( 40 MW )

-

21/03/1994
Unit 2 ( 40 MW ) - 21/11/1994
Unit 3 ( 40 MW ) - 11/01/1995

2.0 GANGREL  HYDEL POWER STATION ( 4 X 2.5  MW  )

The units of 4x2.5 MW Hydel power Station Gangrel were commissioned during 2004-05. The date of commissioning of units are given below:-

     
 
Unit 1 ( 2.5 MW )

-

02/04/2004
Unit 2 ( 2.5 MW ) - 29/06/2004
Unit 3 ( 2.5 MW ) - 17/10/2004
Unit 4 ( 2.5 MW ) - 05/11/2004
 
     

3.0 SIKASAR  HYDEL POWER STATION ( 2 X 3.5  MW  )

The units of 2x3.5 MW Hydel power Station Sikasar were commissioned during 2006-07. The date of commissioning of units are given below:-

     
 
Unit 1 ( 3.5 MW )

-

03/09/2006
Unit 2 ( 3.5 MW ) - 03/09/2006
 
     

 

 

| Back |