1. |
Board’s prescribed application form in three copies. |
|
|
|
|
|
|
2. |
Site sketch/map indicating location and point of supply in 3 copies. |
|
|
|
|
|
|
3. |
Land documents : |
|
|
|
(a) Khasra map, Khasra record B-I, P-II.
(b) Sale deed of land (Registration).
(c ) Copy of Index (Land transfer documents). |
|
|
|
|
|
|
|
For declared industrial area : |
|
|
|
|
|
|
|
(a) Allotment letter from industrial development authority.
(b) Possession receipt of land.
(c) Copy of agreement with financial institute. |
|
|
|
|
|
|
4. |
Consent/NOC from pollution control Board of State Government. |
|
|
|
|
|
|
5. |
Approval of competent authority for land for industrial purpose. |
|
|
|
|
|
|
6. |
If the land is on rent or on lease then rent/lease deed shall be on requisite stamp paper and registered under Registration Act for atleast 30
years |
|
|
|
|
|
(B)
|
|
Documents required for partnership firm : |
|
|
|
|
|
|
1.
|
Copy of registered partnership deed. |
|
|
|
|
|
|
2.
|
Power of Attorney on requisite stamp paper for authorizing the signatory authority to sign on application, agreement, undertaking etc. |
|
|
|
|
|
(C)
|
|
Documents required for public/private limited company : |
|
|
|
|
|
|
1.
|
Memorandum of articles. |
|
|
|
|
|
|
2.
|
Company resolution for authorizing signatory/Attorney authorised to sign application, agreement and other documents. |
|
|
|
|
|
(D)
|
|
For Co-operative Society : |
|
|
|
|
|
|
1.
|
A certified copy of the by-laws of Co-operative Society. |
|
|
|
|
|
|
2.
|
Certified copy of certificate of registration from Registrar of Co-operative Society. |
|
|
|
|
|
|
3.
|
Resolution for requirement of H.T. power. |
|
|
|
|
|
|
4.
|
Resolution regarding assigning authorised signatory with name and designation. |
|
|
|
|
|
(E)
|
|
Load Details : |
|
|
|
|
|
|
1.
|
Details of load required machinery-wise and total connected load. |
|
|
|
|
|
|
2.
|
Copy of project report. |
|
|
|
|
|
|
3.
|
Position of procurement of plant and machinery. |
|
|
|
|
|
|
4.
|
Employment details like officers/managers, officials and labour. |
|
|
|
|
|
|
5.
|
Financial details, status, Bank finance documents. |
|
|
|
|
|
(F)
|
|
Permission from Electrical Inspector after installation of Sub-Station and electrical equipments
etc. |
|
|
|
|