Salient Points in respect of Transmission Works
 
Position As on Dec' 2006
S.No. Particulars Position as on 1/12/2000 Position as on 31/03/01 Position as on 31/03/02 Position as on 31/03/03 Position as on 31/03/04 Position as on 31/03/05 Position as on 31/03/06 Added during 2006-07 Position as on 31/12/06
                     
1 2 3 4 5 6 7 8 9 10 11
                     
1 400 KV Sub Station                  
i)    No. of Sub Station 1 1 1 1 1 1 1 -- 1
ii)   No. of X'mers 3 3 3 3 3 3 3 -- 3
iii)  Total MVA 945 945 945 945 945 945 945 -- 945
                     
2 220 KV Sub Station                  
i)    No. of Sub Station 5 5 5 6 6 7 8 1 9
ii)   No. of X'mers 12 12 12 13 14 16 18 1 19
iii)  Total MVA 1350 1350 1350 1450 1610 1930 2250 160 2410
                     
3 132 Sub Station                  
i)    No. of Sub Station 20 20 23 28 33 34 40 (-1) 2 41
ii)   No. of X'mers 46 46 49 59 66 73 81 5 86
iii)  Total MVA 1257 1264.5 1384.5 1752 2072 2353 2653 247.5 2900.5
                     
4 HVDC Sub Station                  
i)    No. of Sub Station 1 1 1 1 1 1 1   1
ii)   No. of X'mers 6 6 6 6 6 6 6   6
iii)  Total MVA 243 243 243 243 243 243 243   243
                     
5 Capacitor Banks (MVAR) 94 94 94 254 329 349 474 120 594
                     
6 400 KV Lines (Ckt KM) 277.00 277.00 277.00 277.00 277.00 277.00 277.00   277.00